Scheduling Problem

  • It is a problem of determining the minimum completion time for a project given its events.

Earliest Start Time (EST)

  • The earliest possible time that an activity can start.
  • The earliest finishing time of an activity = EST of an activity + Duration of an activity

Forward Scanning

  • Forward scanning is a methodical process for finding the earliest start time (EST) for each activity in an activity diagram. The process works as follows: